Following a challenging period of weather-related delays, we’re pleased to report that work on the irrigation project is now progressing extremely well. The recent spell of dry weather has made a significant difference on site, allowing the team to accelerate works and access areas that were previously too wet to operate on.
Excellent Progress Across the Course
To date, substantial ground has been covered. Installation works are now complete on:
2nd Tees
2nd Fairway pipework (with approximately half of the sprinklers installed)
2nd Green
All of Hole 3
All of Hole 7
Hole 13 (pipework installed, with green sprinklers to follow)
12th Green
18th Tees
In addition, the new water main has been successfully installed, and all but approximately 100 metres of the mainline pipework is now in place. Improved ground conditions have also allowed us to roll and reinstate previously inaccessible areas, enhancing overall course presentation.
What’s Happening Next
Work continues at a strong pace, with clear plans for the coming weeks:
Next week (W/C 23rd):
Completion of remaining sprinkler installation on the 2nd Fairway
Progression onto the 17th hole, with fairway and green works running through to Thursday
Following the Irritech visit, works will commence on the 14th hole
The following week (W/C 30th):
Completion of the 14th hole
Progression onto the 1st hole and 18th Green
Week after (W/C 6th):
Completion of the 18th hole
Works on the putting and chipping green areas
Final Phase
The final stages of the project will include:
Site-wide snagging
Additional rolling and surface refinement
Full system testing, including overnight irrigation cycles
Importantly, the system has remained live throughout the project, and we do not anticipate any issues during commissioning.
Supporting the Course as Conditions Improve
Water is now available across all areas of the course, meaning irrigation can be utilised wherever required as the weather continues to improve. The team is on hand to support this as needed, ensuring optimal playing conditions are maintained.